26-20 Gru891821B (Grundy)
See the original posting, the buyer’s contact details, and thousands more contracts like this one
Free account. Already have one? Log in
Description
Completion Dates: Construction: September 15, 2027 Seeding: November 30, 2027 (Structure and Buffer Seedings must follow the seeding period stipulated in the Technical Specifications) This project is for a nutrient reduction wetland. In general, the work involves, but is not limited to, selective clearing, excavation, grading, tied concrete block mat installation, tile installation, water control structure, riprap, and seeding. This project includes about 11,500 cubic yards of excavation, 12,700 cy of earthfill, installation of 14,800 square feet of tied concrete block mat, two water control structure installations, 4650 linear feet (LF) of tile installation, 220 tons of riprap installation in various sizes, and 14.4 acres of seeding. The estimated construction cost range for this project is $400,00 to $450,000.