171/23125.CTS; Jerome Hart Building - Chilled Water Upgrades
See the original posting, the buyer’s contact details, and thousands more contracts like this one
Free account. Already have one? Log in
Extended to Nov 18, 2026 by a later notice
See the original posting, the buyer’s contact details, and thousands more contracts like this one
Free account. Already have one? Log in
Extended to Nov 18, 2026 by a later notice
The project is located at the Jay Lively Activity Center in Flagstaff, AZ. The scope of work includes selective demolition of existing water-cooled chillers, evaporative coolers, pumps, air control de…
Installation of new air cooled chillers and pumps to serve the Education Building and Jennett Addition.
Provide labor and materials to replace (5) chilled water air handlers complete with new ductwork, VAV boxes, air distribution, and controls. New ceilings, lighting, and fire protection systems are als…
The scope of the chilled water plant replacement consists of the demolition of the existing chilled water plant (building 16a) and construction of a new multi-story chilled water plant to include chil…
The scope of the chilled water plant replacement consists of the demolition of the existing chilled water plant (building 16a) and construction of a new multi-story chilled water plant to include chil…
General work description: This Project addresses system aging, operational deficiencies, and deferred maintenance through a targeted program of capital renewal and system optimization. The work includ…