Federal Contract

DESC2103C - Bulk Fuel Storage Tanks Phase II Yokota Air Base, Japan

See the original posting, the buyer’s contact details, and thousands more contracts like this one

Free account. Already have one? Log in

Get started

Agency

DEPT OF THE ARMY

NAICS Code

237120

Department

DEPT OF DEFENSE

Solicitation Type

Presolicitation

Solicitation #

W912HV26RA009

PSC Code

Y1NA

Division

W2SN ENDIST JAPAN

Posted

Tue, July 14, 2026

Response Deadline

Mon, August 31, 2026

Extended to Jan 25, 2027 by a later notice

Description

The U.S. Army Corps of Engineers, Japan District (POJ) is providing a PRE-SOLICITATION notice for an upcoming Request for Proposal (RFP). This is not a solicitation. PROJECT INFORMATION Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II Project Location: Yokota Air Base, Japan Project FSC: Y1NA - Construction of Fuel Supply Facilities Project NAICS: 237120 - Oil and Gas Pipeline and Related Structures Construction Project Magnitude: Between �2,500,000,000 and �10,000,000,000 (Japanese YEN) Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment. The product recovery pump will return reclaimed fuel back through receipt filtration to the bulk storage tanks. SOLICITATION INFORMATION: Procurement Method: The Government will issue a Request for Proposal (RFP) Solicitation utilizing the Lowest Price Technically Acceptable source selection procedures. The Government a…

Notice history (7)

  1. Jul 14, 2026PresolicitationDue Aug 31, 2026Viewing
Show 3 earlier notices
  1. Aug 12, 2026SolicitationDue Jan 25, 2027

    DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan

    Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment. The product recovery pump will return reclaimed fuel back through receipt filtration to the bulk storage tanks.

  2. Aug 12, 2026SolicitationDue Jan 25, 2027

    DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan

    Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment. The product recovery pump will return reclaimed fuel back through receipt filtration to the bulk storage tanks.

  3. Sep 9, 2026SolicitationDue Jan 25, 2027

    DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan

    Update 10 September 2026: Attached Pre-Proposal Conference Slides. Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment. The product recovery pump will return reclaimed fuel back through receipt filtration to the bulk storage tanks.

  1. Sep 13, 2026SolicitationDue Jan 25, 2027

    DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan

    Update 14 September 2026: Attached Site Visit Roster. Update 10 September 2026: Attached Pre-Proposal Conference Slides. Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment. The product recovery pump will return reclaimed fuel back through receipt filtration to the bulk storage tanks.

  2. Sep 25, 2026SolicitationDue Jan 25, 2027

    DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan

    Update 25 September 2026: Preliminary RFI Response Report has been posted to PIEE. Update 14 September 2026: Attached Site Visit Roster. Update 10 September 2026: Attached Pre-Proposal Conference Slides. Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment. The product recovery pump will return reclaimed fuel back th

  3. Oct 19, 2026SolicitationDue Jan 25, 2027

    DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan

    Update 19 October 2026: Updated RFI Response Report has been posted to PIEE. Update 25 September 2026: Preliminary RFI Response Report has been posted to PIEE. Update 14 September 2026: Attached Site Visit Roster. Update 10 September 2026: Attached Pre-Proposal Conference Slides. Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building. The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mo