20017 - Stormwater Pump Station #6
See the original posting, the buyer’s contact details, and thousands more contracts like this one
Free account. Already have one? Log in
Description
The work includes the demolition, replacement, and relocation of electrical control systems and equipment from the pump station control room to the existing generator building. Also included are miscellaneous electrical and SCADA control work and all associated site work, including maintenance of traffic. The Contractor will be required to keep the pump station in operation to the maximum extent practical during construction. A bypass pumping system capable of handling a minimum of 2,000 GPM will need to be designed, installed, and maintained by the Contractor for the period between the removal of existing electrical equipment and controls and the start-up and acceptance of the new electrical equipment and controls. The Contractor will be required to clean the wet well prior to final completion of the project. Cleaning shall be done using the inlets in the travel lane while personnel access will be from the center of Tidewater Drive.