Tiger Pass Dredging Over Utility Corridor, Plaquemines Parish,
See the original posting, the buyer’s contact details, and thousands more contracts like this one
Free account. Already have one? Log in
Description
Description and Magnitude of Work is as follows: The work consists of the removal and satisfactory disposal of dredged material excavated from the Tiger Pass Bar Channel and identification of utilities, within the limits shown on the contract drawings. (The estimated time of completion is 135 calendar days after receipt of Notice to Proceed. The solicitation will include 5 drawings and specifications). No dike work is included with this project. The bid opening will be conducted virtually, please see Section 0010 for Instructions to Bidders.